Related
Sites
   
   
   
   
  Boundary Map
  Project Area
  Tentative Schedule
  Meeting Map
  Breakout Group Maps
  Aerial Photo
   
  Chestnut Lane Road Project
   Main Page
   

 

 

Chestnut Lane

 


May 18, 2006 Meeting Summary

 

 

The Mecklenburg-Union Metropolitan Planning Organization’s staff in conjunction with the Town of Indian Trail, Town of Stallings, Union County, Town of Weddington, and NCDOT hosted a public meeting on May 18, 2006, to present staff findings and recommendations on a short term solution and preferred long term alignment choice.  Approximately twenty-four individuals attended the meeting held at Antioch Elementary School from 6:00 pm to 8:00 pm. 

The meeting began at 6:15pm with staff presenting information listed below:

  • Purpose of the realignment

  • Purpose of the study

  • Why define an alignment

  • Summary of what has transpired to date

  • Citizen issues and concerns

  • Recommended short term solution

  • Recommended long term solution

During and following the presentation staff responded to citizen inquires.  Board of Transportation representative Larry Helms was present and participated in the question and answer session.  Subsequent to the formal presentation citizens were encouraged to meet with staff one-on-one to discuss additional issues, concerns, or share comments. 


STAFF RECOMMENDATIONS

Short-term recommendation:

BACKGROUND:       
The Town of Stallings, NCDOT and a developer have combined efforts and resources to develop a plan to improve the intersection configuration at Weddington-Matthews Road and Antioch Church Road. 

A developer has been granted approval from the Town of Stallings to build a commercial shopping center on a parcel adjacent to the Citgo gas station at the corner of Weddington-Matthews Road and Antioch Church Road.   As part of the development process, intersection improvements will ultimately correct and enhance mobility.  Preliminary designs have been submitted to the Town of Stallings and necessary permits needed to begin construction have been issued (permits will expire in six months).  Currently the developer is negotiating with an anchor tenant and does not have a tentative construction schedule available at this time.   

Prior to partnering with the Town of Stallings and the developer, NCDOT completed a study which justified the need to make intersection improvements.  NCDOT identified a potential funding source and began the process for securing funds.   


RECOMMENDATION:
Proposed improvements included reconfiguring the existing “T” intersection to create a four-way intersection with a traffic signal.  The fourth leg of the intersection is also the entrance into the proposed shopping center.  The geometry of the intersection will be improved to allow for better right turn movements from Weddington-Matthews Road onto Antioch Church Road and left turn movements from Antioch Church Road onto Weddington-Matthews Road.  Turn lanes will be added on all legs of the intersection. 

In the event the developer is unable to develop his site, NCDOT will continue to pursue the existing funding source and examine other funding sources to improve the intersection. 

Staff supports the proposed recommendation to reconfigure the intersection of Weddington-Matthews Road and Antioch Church Road, creating a four-way intersection.

 

Long-term recommendation:

BACKGROUND:       
Over the past year staff has held public meetings, received comments, collected and analyzed data in an effort to make a sound decision on a preferred alignment.  Some of the data included:

Tag Survey – An inventory of motor vehicle flow at an intersection or other roadway location.  At intersections, vehicular movements are generally classified by turning and straight movements. 

Intersection Analysis – Examine volumes of vehicular traffic at intersections to determine if they are or not great enough to justify signalization. 

2030 Model Volumes – A projection of anticipated traffic volume levels once the 2030 roadway network is complete and functioning. The 2030 network is proposed to be completed between January 1, 2021, and December 31, 2030. 

Existing and future growth and development – A review of development patterns and trends in the study area and their existing and potential effect on the roadway network.   

Preliminary Engineering – Computer generated layout of a road alignment which profile incorporates topography, curvature, slope, design speed and other helpful information.  All alignments underwent a detailed analysis to ascertain their feasibility and develop a specific, defined alignment.   This process will enable the right of way corridor to be protected by the townships and municipalities as development occurs around it. 

During the presentation it was noted that the long-term alignment is currently unfunded and has a horizon year of 2030, meaning that the proposed alignment should be built between January 1, 2021 and December 31, 2030, provided financial support is available.  

Several alignment options created by citizens and staff were evaluated for their viability.   Many of the alignment choices, although technically feasible to construct, did not support the findings from the data collected.  Specifically, they did not allow for the necessary through movements that future traffic volumes indicate will be necessary. Other contributing factors that made alignment options unworkable included proposed residential and commercial development, utility power line poles, and proposed elementary schools recreational fields.

 

RECOMMENDATION:
Staff presented two alignment alternatives; Option 1  (Extension of existing Chestnut Lane west of Weddington-Matthews Road, meandering southwest until reaching its terminus at Tilley Morris Road) and Option 2  (Realignment of Chestnut Lane as it appears on the Mecklenburg-Union Thoroughfare Plan, beginning at a point where Chestnut Lane and Red Barn Trail intersect then meandering southwest until reaching its terminus at Weddington-Matthews Road and Antioch Church Road creating a four way intersection). 

Preliminary design of each alignment revealed that both were feasible options. Additional data collected based on vehicle turning movements indicated that a significant amount of turns being made were from Tilley Morris Road onto Chestnut Lane and the reverse.  Projected two-way 2030 volumes along Chestnut Lane and Tilley Morris Road are estimated to be in excess of 17,000 vehicles per day by the year 2030.  Data suggest that the existing alignment as shown on the Thoroughfare Plan is appropriate to future growth and development in the area.   

Staff recommended Option 2 (Modified Alignment) – The proposed alignment has been shifted in an effort not to encroach on existing structures and minimize the impact of the alignment on affected properties.

 

NEXT STEPS: 

Staff will present its findings and recommendation to the Technical Coordinating Committee (TCC) on July 6, 2006 at 10:00 am in the Charlotte-Mecklenburg Government Center.  The TCC will forward a recommendation to the Metropolitan Planning Organization (MPO) for final approval.  The MPO will meet on July 19, 2006 at 7:00pm in the Charlotte-Mecklenburg Government Center.

Please note that the public can attend TCC meetings, however, it is at the discretion of the TCC chairman if public comment will be permitted.  MPO meetings are public meetings where citizens are granted an opportunity to voice their opinions about transportation issues.  Please note that a time limit for each speaker is enforced.

 

 

PUBLIC INVOLVEMENT:
MUMPO encourages public participation in the transportation planning process and employs the assistance of citizens to ensure that the overall transportation system reflects the desires of the public  If you would like further information, please contact Barry Mosley of the MUMPO staff at (704) 336-8314 or via e-mail at: bmosley@ci.charlotte.nc.us.

 

Return to the Chestnut Lane Road Project Main Page

 

 

 

 


 

 

Contact Us | Legal Notices 
Official Mecklenburg-Union Metropolitan Planning Organization Web Site

 

 

For more information regarding Mecklenburg-Union Metropolitan Planning Organization,
Please contact:
Barry Mosley
600 E. Fourth Street
8th Floor
Charlotte, NC 28202-2853
(704) 336-2205